Cutover plan
In a software or website migration, a cutover plan is the ordered, timed list of steps for switching users from the old system to the new one. It names an owner for each step, the checkpoints at which the team confirms it is safe to continue, and the point of no return after which going back is no longer practical.
The longer version
A cutover is the short window in which one system stops being the live one and another starts. The plan for it is a runbook read from top to bottom, in which each line has a start time, an expected duration, one named owner and a way of confirming it is done. For a website migration the lines might read: lower the time to live on the DNS record two days ahead, announce the maintenance window, put the old site into read-only mode, take the final copy of the database and import it, run the checks on the new site at its temporary address, switch DNS, verify the redirects from the old URLs, reopen for writes, and watch errors and orders for the agreed period. The order is the substance of the plan, because several steps are safe only after the one before them.
Checkpoints divide the list. At each one a named person compares what has happened with what the plan expected, such as the row counts after the import or the result of a smoke test, and decides whether to continue. These are small go/no-go decisions taken inside the window, separate from the release decision that allowed the cutover to begin. One checkpoint matters more than the rest: the point of no return. Before it the old system is intact, and going back means abandoning the remaining steps. After it the new system has accepted data the old one never saw, and going back would lose that data or require migrating it in reverse. The plan marks that line and states what must be true before anyone crosses it.
The cutover plan and the rollback plan are two documents for one night. The first describes the way forward and the second the way back, and each checkpoint in the first says whether the second is still available. Rehearsal turns the timings from guesses into measurements: a trial import against a copy of production data shows whether the final copy takes ten minutes or three hours, and that result sets the length of the maintenance window. Approaches differ in how much has to happen inside the window. A big-bang cutover moves everyone at once. A phased cutover moves groups of users or sections of a site in turn, and a parallel run keeps both systems live for a period and compares their results. All three need the same plan for the moment each switch is made.
AWS Prescriptive Guidance, written for cloud migrations, gives the cutover stage five steps that apply to most switches: an ingestion freeze, a final backup of the old system kept for the rollback, a data sync, the routing change that sends users to the new environment ("for example, updating DNS records or changing load balancer targets"), and testing. It asks for task definitions and durations, task owners and the sequence in a cutover workbook, with a RACI matrix saying who is responsible, accountable, consulted and informed for each task, and an operational readiness review before the window opens. Its timing advice is to cut over when there are the fewest users, balanced against when support teams are available. It also notes that as the cutover window shrinks, the complexity of the cutover grows, so a short window needs more planning. Afterwards a warranty period, which the guide puts at typically one day to one week, keeps the project team on call while users report what the checks missed. Reports in that period are most useful when they say which system the user was on, the old one or the new one, since the two can be live side by side.
Common questions
What is a cutover plan?
A cutover plan is the step-by-step schedule for moving live use from an old system to its replacement. Every step has a time, an owner and a completion check, and the list includes the checkpoints where the team decides whether to carry on and the point after which reversing is no longer practical.
What should a cutover plan include?
A cutover plan should include the steps in order with start times and durations, one owner per step, the freeze on changes to the old system, the final data migration, the verification checks, the switch itself, the checkpoints and their pass conditions, the point of no return, the communication to users and support, and the monitoring period that follows.
What is the difference between a cutover plan and a rollback plan?
A cutover plan sets out how to get from the old system to the new one. A rollback plan sets out how to return if the move fails. The two are used together: each checkpoint in the cutover is a place where the team either continues or invokes the rollback, up to the point where returning stops being possible.
What is the point of no return in a cutover?
The point of no return is the step after which the old system can no longer simply be switched back on. In a migration it arrives when the new system starts accepting writes, because new orders, sign-ups or edits then exist only there. Past that step a failure is repaired on the new system and not reversed.
How do you rehearse a cutover?
Rehearsal means running the whole plan against a copy of production data in a non-production environment, with the people who will carry it out on the night. Each step is timed, the verification checks are run for real, and the rollback is exercised from at least one checkpoint. Steps that surprised anyone are rewritten before the date is confirmed.
What is the difference between go-live and cutover?
Cutover is the whole controlled switch, from the freeze on the old system through the data move, the checks and the change of routing. Go-live is the moment inside it when the new system opens to its users. A cutover plan therefore contains the go-live, along with the steps before it and the monitoring after it.
What is a freeze in a cutover plan?
A freeze stops changes to the old system so that the data being moved stays still. Plans often stage it: a soft freeze asks people to avoid non-essential changes, and a hard freeze is the point at which, in Washington State University's Workday cutover, staff stop entering information into the old system and the new one takes over.
What happens if a cutover fails after new data was written?
Once the new system holds data the old one never saw, a plain rollback would lose it. AWS lists the options: fail forward and fix the new system, run a dual-write strategy so both systems receive the data, or restore from a native backup. The plan should name who makes the call between fixing forward and rolling back.