Change control

In software and project delivery, change control is the process that decides what happens to every proposed change to an agreed baseline, such as a scope, a design or a production system. Each request is logged, assessed for its impact, then approved, rejected or deferred by someone with the authority to decide, and the decision is recorded.

The longer version

The process is a short loop that every request passes through in the same order. The request is logged, so that it has a number and cannot be lost in an email thread. Its impact is assessed: what it touches, what it costs, what it does to the schedule and what risk it adds. An authority decides. The decision is recorded with its date and its reason and sent to everyone who planned around the old version. If the answer is approval, the plan, the budget and the affected documents are updated before the work starts, and afterwards somebody confirms that what was built is what was approved. What the loop protects is the baseline, meaning the last version of the scope, design or system that everyone agreed to. The Association for Project Management defines change control in exactly those terms, as the process through which all requests to change the approved baseline are captured, evaluated and then approved, rejected or deferred. The ISTQB Foundation Level syllabus, version 4.0.1, uses the word in this sense for test assets: a configuration item approved for testing becomes a baseline and "can only be changed through a formal change control process".

A change control board is the group that makes the decision when one person should not. It brings together the people who can speak for each consequence of a change: the budget holder, the delivery lead, someone for the technical side and someone for the users. A large programme convenes it on a calendar. A small project needs the function without the committee: two named people, one from the client and one from the supplier, with a rule about the size of change each may approve alone. Thresholds keep the process in proportion. A copy correction or a change inside the agreed estimate goes through on the delivery lead's word, and anything that moves the price, the launch date or the list of deliverables goes to the client's sponsor. Without thresholds every small edit waits for a meeting, and people learn to go around the process. Urgency needs a rule of its own. A fix for a live site that is losing orders cannot wait for the next sitting of a board, so one named person may approve it alone, and the change is logged and reviewed in the days after, which keeps the emergency route from becoming the usual one.

On a client project the process protects both sides. The client keeps a budget and a date that move only when they agree, and a record of what they asked for and what it cost. The supplier is protected from scope creep, the slow growth of a project through additions nobody priced, and from the argument at the end about whether a feature was included. Testers gain as well, since an approved change is announced before it lands and the test cases can be updated to match. Change control has a meaning of its own in regulated manufacturing, where a pharmaceutical quality system applies it to changes in a validated process, and in IT operations, where it governs changes to live infrastructure. The software project sense shares the logic and differs in what the baseline is. The process fails when it turns into theatre: every request is approved, or the log is filled in after the work is done, and the record no longer shows that anyone decided anything.

Common questions

What is change control in project management?

Change control in project management is the procedure for handling every proposed change to an agreed baseline. A request is logged, its effect on scope, cost, schedule and risk is assessed, an authorised person or board approves, rejects or defers it, and the outcome is recorded and communicated before any work on the change begins.

What is a change control board?

A change control board is a group with the authority to approve or reject proposed changes on behalf of a project or a system. Its members represent the parties a change would affect, such as the budget holder, the delivery lead, a technical lead and a user representative. On a small project two named people can perform the same function.

What is the difference between change control and change management?

Change control is the decision process for individual changes: assess, approve or reject, record. Change management is the wider phrase and has two senses. In IT operations it covers the whole handling of changes to live services, including scheduling and review afterwards. In organisations it means helping people adopt a new way of working. Change control is one mechanism inside the first, and the Association for Project Management calls it a subset of overall change management.

What are the steps in a change control process?

The steps are to log the request, assess its impact on scope, cost, schedule and risk, decide whether to approve, reject or defer it, record the decision with its reason, update the plan and the affected documents, carry out the change, and verify that what was delivered matches what was approved. The record earns its keep later, when someone asks why the scope or the date moved.

Does an agile team need change control?

An agile team handles most change through its backlog: the product owner reorders or replaces items, and the plan absorbs the change at the next iteration. Formal change control still applies to whatever sits outside the backlog's reach, such as a fixed contract price, a committed launch date, a regulated system or a production environment shared with other teams.

What is change control in QA?

In software quality assurance, change control keeps the test basis stable: requirements, designs and test assets approved for testing change only through a recorded decision, so testers know which version they are checking and can update their cases when a change is approved. In pharmaceutical and medical device quality, the same phrase names a regulated procedure for changes to validated processes, which is a separate discipline.