How to avoid scope creep one comment at a time

How to avoid scope creep on a web build: sort each piece of client feedback into defect, change or question before anyone fixes it, and price the changes.

Four clear glass cubes sit inside a square glass tray, and a fifth orange cube rests just outside its rim

To avoid scope creep on a website or web app build, sort every piece of feedback against the written acceptance criteria before anyone fixes it. Each comment is a defect, a change or a question. Defects are fixed, changes go through a change request with their cost, and questions are answered in writing.

Scope creeps in through feedback, where nobody is pricing

A large request gets noticed. When a client asks for a booking system halfway through a brochure site, everybody knows it is new, and somebody prices it. The work that slips through is smaller and arrives in a review round, worded as a correction: “the product page should also show customer reviews”. It is filed with the bugs and fixed the same afternoon, and neither the budget nor the launch date moves.

The Project Management Institute’s Pulse of the Profession 2018 report describes scope creep as “the uncontrolled expansion of product or project scope without adjustments to time, cost, and resources”. The last clause does the work. Growth with an adjustment is a scope change, which the Association for Project Management’s glossary defines separately as “Any change in a project scope that requires a change in the project’s cost or schedule”. Growth with no adjustment is creep.

The same report, a survey of project professionals in industries from government to construction, says “52% of the projects completed in the past 12 months experienced scope creep or uncontrolled changes to the project’s scope”. The figure dates from 2018 and is not specific to web builds.

Project management guides list much the same causes: a scope that was never written down, too many stakeholders with no single approver, changes accepted in chat or in passing, and customer feedback that arrives late. On a web build those causes meet at one point, a review comment that reaches a developer before anybody has compared it with the agreement.

A scope statement, a signed agreement and a change process are all written at the start of a project. None of them is present when a developer opens a ticket that says “should also”, and creep is stopped or let through at the moment that ticket is classified.

Every comment is a defect, a change or a question

Classifying a comment means reading it against what was agreed. The agreement is the acceptance criteria and the out-of-scope line on each story, which the user story template keeps as fields, the approved design, and the team’s definition of done for standards no single story states, such as the browsers supported.

A defect means the build does not do what was agreed. A change means the build does what was agreed and the comment asks for a different agreement. A question means the written agreement does not settle the matter. The table sorts five comments from the review of an online shop.

The commentClassThe reasonWhat the client hears
“The contact form does not send on my phone.”DefectA criterion says a visitor can send the form, and that browser is on the supported list“That is ours to fix, inside the price.”
“The product page should also show customer reviews.”ChangeThe criterion lists what the product page shows, and reviews are absent from the list“Reviews are an addition to what we agreed. Here is the cost and the new launch date.”
“Could the basket show the delivery cost?”DefectA criterion already says the basket shows the delivery cost“That was agreed and we missed it. We will fix it inside the price.”
“What should a visitor from another country see?”QuestionNo criterion mentions visitors from abroad“The agreement does not say. Here are two options, and only the first fits the current estimate.”
“The header should stay visible when I scroll.”ChangeThe approved design shows a header that scrolls away“That is a small change to the approved design. We will make it at no charge and record it.”

The third row is worded as a request and is a defect, the reverse of the second, so wording is no guide in either direction. Why a defect is defined against a written expectation is argued in bug vs feature is settled by what was written down.

A question needs the most care, because a developer left alone with it answers it by building something. The fourth comment goes to whoever owns the criteria on the client side, the answer is written into the story, and the comment is then a defect or a change like any other. How to write acceptance criteria a build can fail argues for planning one such round after the first working build.

The sorting happens before the fix, one comment at a time

If a comment is satisfied by making the build match a sentence that already exists, it is a defect. If satisfying it means writing a new sentence first, it is a change. If nobody can find the sentence, it is a question.

The timing matters more than the test. Once a change has been built as a fix, its price has to be raised over work the client already has. So one named person on the delivery side labels each comment before it reaches a developer. A developer handed an unlabelled comment will fix it, because fixing is the job.

Labelling needs separate items. One email with fourteen points mixes all three kinds and invites a single reply. This is the one place Notarus has a part. When feedback is filed through the widget, the client marks what is wrong on the page they are looking at, and each report enters the first status of the board as its own ticket. The widget captures the page, and console logs, network activity, page URL, viewport and browser travel with the report as captured evidence. Capture settings, browser support and performance budgets decide what is available. The ticket shows what the client saw, and a person still reads the criteria to decide whether it is a defect or a change.

The team’s own additions are sorted the same way

Creep also starts inside the team. A developer adds an animation nobody asked for, or a designer reworks a screen the client already approved, because it seemed like an improvement. Project managers call this gold plating, and it spends the budget on work outside the agreement as surely as a client’s “should also”. The same test settles it. If the addition needs a new sentence in the agreement, it is a change, and the client is asked whether they want it before it ships.

A change is welcome, and it arrives with its price

Customer reviews on the product page may be a good idea. The answer to the request is yes, with its cost and its effect on the launch date attached. A change request is the document that carries both, and change control is the loop that puts it in front of somebody with the authority to spend the money. A client told “that is out of scope” hears a refusal. A client told “yes, and here is the cost” has been handed a decision that was always theirs.

The client has more than one answer available. A priced change can be approved, deferred to a later phase, declined, or swapped for something of similar size that leaves the agreement so the launch date holds. Each answer is written down the same way, including the refusals, so the request is not raised again as new in the next round.

Small changes need a threshold, or every tweak waits for a signature. A delivery lead can approve a minor change alone, and can give it away. What keeps a gift from turning into creep is the record. The change is logged as a change, at no charge, with the estimate it would have carried.

An approved change also rewrites the agreement. It adds or alters a criterion, so the client’s earlier approval no longer describes what is being built, a point argued in a client approval must say what it covers.

A product team with an internal stakeholder sends no invoice, and the price is paid in the plan. A change displaces something from the sprint or the release, and the stakeholder who asked for it chooses what moves out.

Four other practices exist to make the sorting possible

Classifying feedback is the first practice, and the other four earn their place by serving it. They are ranked by what fails first when one is missing.

OrderPracticeWhat goes wrong without it
FirstOne named person classifies every comment before it is worked onNew requirements are built as fixes
SecondAcceptance criteria and exclusions are written before the buildEvery comment is a question, and nothing can be called a change
ThirdEach side names who approves a change, and up to what size aloneA change is agreed by somebody who cannot spend the money
FourthEvery change is logged with its cost and its effect on the date, free ones includedNobody can say at launch what was added
FifthFeedback arrives as separate items, each on the page it concernsThree kinds of comment get one reply

Written criteria come second because they prevent nothing by themselves. A project can hold a signed scope and a full set of criteria and still creep, if comments go straight to developers. Separate items, the fifth row, also show when two reviewers have contradicted each other, which conflicting stakeholder feedback is two pages covers.

Sorting moves the argument earlier and does not end it

The method depends on a written agreement. Where the brief was a conversation, every comment is a question until somebody writes down what both sides thought they had agreed. It also takes a person’s attention for every comment in every round, and that time belongs in the estimate.

A client can dispute a label. The hardest cases are comments on something the criteria half cover, where a fair reading goes either way. Those are decided by two named people, one from each side, and the agency will absorb some of them. What changes is the size and the date of the disagreement. It concerns one comment and one sentence, and it happens in the week the comment was made, well before the invoice and the UAT sign-off.

A project run this way still grows. Each addition was chosen by the client with its cost in view, which is the adjustment the PMI definition says creep lacks.

Common questions

How do you avoid scope creep?

Avoid scope creep by classifying every piece of feedback against the written acceptance criteria before any work starts on it. A comment the build fails is a defect, a comment asking for something the agreement never said is a change with a cost, and a comment the criteria cannot settle is a question for whoever owns them.

What is scope creep?

The Project Management Institute describes scope creep as the uncontrolled expansion of product or project scope without adjustments to time, cost, and resources. On a website or web app build it can look like new requirements delivered as bug fixes, while the price and the launch date stay where they were.

What is the difference between scope creep and a change request?

Scope creep is work added to a project without anyone adjusting the cost or the date. A change request adds the same work in the open. The request is written down, the delivery team states what it costs and what it does to the schedule, and somebody with authority approves it before anything is built.

How do you tell a client that a request is out of scope?

Tell the client what was agreed, confirm that the build does it, and name the request as an addition with its cost and its effect on the launch date. Then ask whether to go ahead. An out-of-scope request gets a priced yes, so the client decides with the figures in front of them.

Is a small change for a client scope creep?

A small change becomes scope creep only when nobody records it. A delivery lead can approve a minor addition and waive the charge, and the project stays under control as long as the addition is logged as a change with the estimate it would have carried. A run of unrecorded favours is work nobody priced.

Who decides whether client feedback is a bug or a change?

One named person on the delivery side classifies each comment by reading it against the acceptance criteria and the approved design. Where the written agreement does not settle the matter, the comment is a question, and the client's approver and the delivery lead answer it together before any work starts.

How do you handle scope creep in agile?

Handle it by making every new requirement a new backlog item. An agile backlog absorbs change by reordering, so a new item displaces another and the cost shows as something that moves out. Scope creep still happens when a new requirement is fixed inside an existing story as though it were a defect, because nothing is displaced and nobody chose the trade.

What is the most common cause of scope creep?

Project management guides name the same few causes: a scope that was never written down, too many stakeholders with no single approver, changes accepted informally in chat or in passing, and feedback that arrives late. They share one mechanism. A request reaches the people doing the work and nobody compares it with the agreement before it is built.

Is gold plating scope creep?

Gold plating is scope creep that starts inside the team: work nobody asked for, added because somebody on the delivery side thought it would improve the result. It spends the budget on something outside the agreement in the same way. The same test applies to it as to a client comment, so the addition is a change and the client decides whether they want it.

The Notarus team

The people who build Notarus. We write up the decisions behind the product when the reasoning is worth more than the changelog line.

Keep reading

Reports with the evidence attached.

Start free, one script tag.

<script src="…/widget.js" data-key="pb_pub_…">